Three-Month SOFR Futures Explained: Prices, Implied Rates and DV01
Three-month Secured Overnight Financing Rate (SOFR) futures are exchange-traded contracts based on business-day-compounded SOFR during a specified reference quarter. They are quoted in the familiar price-equals-100-minus-rate convention. A futures price is a market price reflecting expected overnight financing conditions and risk premia, not the Federal Reserve’s official policy projection.
Key concepts covered
- What SOFR measures
- The CME SR3 contract and reference quarter
- Price equals one hundred minus the quoted rate
What SOFR measures
SOFR is a US dollar overnight secured funding rate published by the Federal Reserve Bank of New York. It reflects the cost of borrowing cash overnight collateralised by Treasury securities in specified repo markets. It is not the federal funds target range and is not the same as a term loan rate. Compounding overnight SOFR observations produces a realised rate over a reference period, which is the economic basis of many derivatives and the CME three-month futures contract.
The CME SR3 contract and reference quarter
The CME SR3 contract uses a quarter spanning specified International Monetary Market (IMM) dates, conventionally the third Wednesdays of the relevant contract months. Its final settlement reflects the business-day-compounded SOFR rate over the contract reference quarter, annualised according to the contract rules. That differs from simply taking the arithmetic average of three monthly SOFR prints. Holidays and calendar-day weighting are addressed by the exchange’s product methodology; a research spreadsheet must not replace these mechanics with an unlabelled approximation.
Price equals one hundred minus the quoted rate
The exchange-style price is 100 minus the relevant annualised percentage rate. If a fictional contract trades at 96.25, its implied contract rate is 100−96.25 = 3.75%. If expectations shift so the quoted rate is 3.65%, the futures price increases to 96.35, a change of +0.10 price points. Under this convention, a long futures position typically benefits from a decline in the priced SOFR rate, all else equal, while a short future benefits from a rise.
How the contract’s basis-point value works
CME specifies that a one-basis-point (0.01 percentage-point) movement in a three-month SOFR futures contract corresponds to $25 per contract. Therefore the ten-basis-point rate decline in the example equates to a ten-basis-point rise in futures price and about $250 gross gain for one long contract, before commissions, margin financing, fees and intraday variation margin. This is a sensitivity calculation; actual trades have minimum price increments and may be executed at different prices.
What changes as the reference quarter unfolds
Before the quarter begins, the rate component mostly reflects market pricing of future daily SOFR. After the period starts, part of the compounded rate is determined by SOFR that has already been observed and part remains sensitive to future overnight rates. As the quarter nears completion, less uncertain time remains. It would be incorrect to read an expiring contract’s 96.25 price as an entirely forward-looking forecast for the next three months if much of its reference quarter has already elapsed.
SOFR futures are not a pure Fed meeting probability
SOFR can differ from the effective federal funds rate due to funding markets, technical balance-sheet factors and secured versus unsecured transactions. A contract’s price also spans a whole reference quarter, while Federal Reserve meetings occur on individual dates. A model extracting meeting probabilities must account for known SOFR observations, relevant day weights, the assumed relationship between SOFR and policy rates and any risk premia. A simple 100-minus-price calculation only returns a contract-equivalent rate.
Quarterly compounding versus monthly averages
For a three-month contract, the exchange compounds overnight observations across the reference quarter. One-month SOFR futures have their own averaging and settlement definitions. An analyst comparing SR1 and SR3 quotations should not combine the numerical rates as though they were identical one-day forward fixings. Rate curve construction requires a careful schedule of settlement windows, known fixings, compounding conventions and futures convexity where relevant. Misaligned windows can create fictitious arbitrage.
Risks beyond directional rates
Futures involve daily margin variation, potentially large gross notional exposure and the possibility of rapid losses from shifting rate expectations. Exchange price limits, liquidity depth, margin requirements and correlation with other rates products can matter. A hedge’s DV01 should be based on actual contract sensitivity and the relevant curve exposure; the quoted $25 per basis point is not automatically the right hedge ratio for a bond that responds to longer Treasury yields.
A reproducible futures review
Record contract symbol, reference quarter, as-of quote, implied rate, current observed SOFR fixings and the relevant rate curve. Reconstruct the pricing from actual settlement rules and quantify the change in the implied rate across each central-bank or macro event. Separate the realised portion of the reference period from the still-forward portion. Include the effect of spread differences between secured funding and policy expectations, and label the numerical exercise as an illustration rather than a real trade.
Worked calculation and comparison
| Measure | Worked value / interpretation |
|---|---|
| Illustrative SR3 price | 96.25 |
| Initial implied rate | 100−96.25 = 3.75% |
| New implied rate | 3.65% |
| New futures price | 96.35 |
| Rate move | −10 basis points |
| One-contract long gross price P&L | +$250 at $25 per basis point |
Figures are hypothetical illustrations, not current prices, forecasts or trading instructions.
Frequently asked questions
Are SOFR futures and fed funds futures identical?
No. They refer to different funding rates and may cover different reference windows.
Why does the price rise when the implied rate falls?
The contract uses 100 minus the rate as its quote convention.
Does 96.25 guarantee SOFR will be 3.75%?
No. It is a market-derived price before final settlement, not a guaranteed outcome.
Is $25 per bp a return on invested margin?
No. It is the specified contract value change for a one-basis-point price move, before costs.
Related Traders MBA Education
Primary references and methodology
Underlying definitions are documented in the references below; worked figures are independently constructed solely for education. The article was prepared with AI assistance and does not claim to have observed live order books, executed hedge transactions or independent brokerage research.
- CME Group: Understanding SOFR futures
- CME Group: Three-Month SOFR contract specifications
- New York Fed: SOFR reference rates
General educational content, not an offer, personal investment recommendation or guarantee of returns. Real trading and hedging introduce significant financial risks.
Stay Ahead of the Markets
Get market analysis, financial news and practical trading insights delivered straight to your inbox.